Comment: minutes from meeting 20180228

...

  1. Sireesh started setting up local environment for robot test and reviewing test cases from previous release. 
    1. will contact Leimeng to know new features; 
    2. Hima will help setup the Portal in local testers machine.
    3. set up new test cases
    4. found some bugs, to work out with the development team
  2. vm11 test environment to check the bugs and to perform testing - Sunder/Leimeng  discovered issue where new function code introduced, but not in DML script. - Lorraine will check
  3. AAF integration with SDC - help Micheal Lando - Sunder/Leimeng  Leimeng will send document to partners (check with Sunder too) ASDC descoped AAF integration
  4. Portal-182 - CLI integration help - Leimeng to setup a working session - Sunder Tattavarada/Former user (Deleted) 
    1. Start working on Jan 31st – Leimeng will organize a call with Sunder/CLI team on Wed 9:00am (Sunder could not join the meeting, when is the next meeting?)
    2. Another working call was made and Making progress
  5. Portal-155 - security issues scan - Nexus IQ and Coverity scans
    1. Need Access on Nexus IQ - Farhan/S
    2. Coverity scan followup with Stephen.terrill@ericsson.com - Farhan
    3. many user stories created regarding this big item, pending to assign to developer. (assigned to Sudeep)
  6. Security issues status from CLM - Sudeep(Nexus IQ)  - Sudeep  - 
    1. pull request made, fixed in portal; but not SDK, new pull request for SDK will be made for what is working
    2. ETA today for pull request - SDK
  7. Plan to release SDK 2.1.0 version and then communicate to partners to update their poms - Sunder/Leimeng - ETA 1/19.  ==> update ETA to 1/25 - Sunder need help to find 
    1. Sunder emailed to LF team - however, LF team asked for latest build reference as the last build is 2 weeks old.
    2. completed SDK 2.1.0 released
  8. Extend Portal-119 to split DB for Portal and SDK - Robert - design session pending and ETA on dev tasks.  - Robert working on it now
    1. Robert is using VM3 for this effort. → 70% done by Robert
    2. Update the deployment scripts with docker image name changes - 
      1. demo repo (heat templates); 
      2. integration repo (CSIT test deployment scripts); 
      3. OOM deployment;
  9. Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - done - Hima will be cleaning up - ETA 1/10.
    1. ECOMP keyword in license text - followup with Catherine - Manoop ETA 2/16 ==> still pending
    2. java class names - we can leave it as is 
  10. JUnit /Sonar coverage to 50% on SDK and Portal. - Deadline March 15th for SDK
    1. SDK - JUnit test coverage reached 14% 19.7% - Hima (pending code review and push to gerrit) - Code need to push to gerrit - 
      Jira Legacy
      serverSystem Jira
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyPORTAL-161
      1. Shireesh will coordinate his team with Hima and Kishore Gujja - done
      2. Local version is up to 24-25%, planning on pushing today - Sitharaman
    2. Portal - target 30% to 50% - Girish/Hari team will continue from Gerrit -
      Jira Legacy
      serverSystem Jira
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyPORTAL-136
      1. Hari is coordinating the remaining code coverage on Portal (right now it is at 44%)48.7%) - Kishore,
      2. Manoop to followup with Gildas on the Sonar upgrade issue which got 2% down for portal form 40 - 38% (this is due to change in sonar calculation with new upgrade).
  11. Discussed remaining JIRA items in great details → portal-151 
    1. (assign priority from items in wiki page to JIRA by Leimeng)
  12. MUSIC integration - add JIRA epic/US - Sunder to provide the % complete
    1. Development is targeting to complete by 02/28
    2. Leimeng to coordinate a meeting to share the MUSIC integration details with testing teams to plan the test strategy for these features.
    3. on-track, couple days to wrap up development
  13. AAF, if AAF is not ready for testing by 2/15, then Portal will not integrated with AAF for Beijing release - Leimeng send email to Sai - Is the AAF instance ready in LAB env to test the integration?
    1. Sunder to followup with Sai 
  14. Defect tracking of Critical and Highs - Naveen and Shireesh to coordinate with Leimeng to test and close them and raise as concern if cannot be closed.
    1. automated testing making progress on VM11 
    2. Sunder will refresh VM11 environment
  15. Beijing Release Planning:
    1. M0 - dev kick-off, Nov 16
    2. M1 - planning Jan 16
    3. M2 Functionality Freeze  →  fill in the contents by Manoop & Leimeng - done
    4. M3 API/Data Model Freeze 
    5. M4 Code Freeze 

...