- This project will deliver a unified set of VNF Guidelines and VNF Requirements.
- The VNF Guidelines and VNF Requirements must be versioned to enable evolution based on operational experience
- The VNF Guidelines and VNF Requirements will support the ONAP Architecture Principles.
- Update the VNF Requirements as prototype RFP text for the ONAP/Beijing release including:
- Hardware Platform Awareness (HPA) Requirements
- HEAT/TOSCA Information Model updates
- Update the VNF Guidelines as for the ONAP/Beijing release
- Update the VNF Requirements as prototype RFP text for the ONAP/Beijing release including:
- Identify a list of features and functionality will be developed.
- The VNF Guidelines and Requirements will support the Release 1 Use Cases.
- Use cases focused on VNF Requirements may be developed in this project, and they will need to be aligned with the ETE Platform use cases.
- Document the VNF Provider Guidelines for VNF Scaleout Use Case for the ONAP/Beijing release
- VNF Guidelines and Requirements are to be refined beyond prototype text (e.g. through EPIC statements, use cases) to deliver test cases and test procedures for us in VNF onboarding & validation. VNF Requirement level use cases to be aligned with ETE platform use cases
- Document the VNF Test Case Descriptions for VNF Package testing for the ONAP/Beijing release
- Identify what is in or out of scope. During the development phase, it helps reduce discussion.
- VNF Guidelines may be forward looking, or include best practices in VNF design and VNF lifecycle processes.
- VNF Requirements from ONAP APIs should be linked to the ONAP Release
- VNF Requirements may include:
- expected operational characteristics ( e.g. security, resilience, upgradeability)
- conditional requirements (e.g. When configured for deployment on High Availability Network Cloud Infrastructure, the VNF Shall …)
- Tool chain improvements
- Develop requirements structure/ metadata to support better linkage / tracking with other ONAP projects
- Develop templates for VNFs to demonstrate VNF Requirements conformance
...
Jira Legacy | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|
...
The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
Date | Project | Deliverable |
---|---|---|
1/8/18 | VNF Requirments | Draft M1 Project Plan available on VNFRQTS Project Wiki |
1/18/18 | VNF Requirments | ONAP Beijing M1 Milestone - planning process complete |
2/12/18 | VNF Requirments | ONAP Beijing M2 Milestone - functionality freeze |
3/8/18 | VNF Requirments | ONAP Beijing M3 Milestone - API data model freeze |
3/29/18 | VNF Requirments | ONAP Beijing M4 Milestone - code freeze |
4/19/18 | VNF Requirments | ONAP Beijing RC0 Milestone |
5/3/18 | VNF Requirments | ONAP Beijing RC1 Milestone |
5/17/18 | VNF Requirments | ONAP Beijing RC2 Milestone |
5/24/18 | VNF Requirments | ONAP Beijing Signoff Milestone |
Team Internal Milestone
This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended to provide these agreements and dates in this section.
...