Objective

How Achieved

Participant Preparation required

Action items out

2Review JIRA Backlog. Participants should be comfortable that they understand the backlog of tasks for our project ( 15 min)

Walk through the JIRA backlog to check for completeness

review:


vnfrqts Epics

vnfrqts User Stories

vnfrqts bugs


3Develop Sprint definition. Participants should be comfortable with an achievable development sprint scope ( 30 min)

as a group select a minimum set of functionality to complete within the next two weeks

based on seed contributions

propose a minimal "getting started" sprint scope.

ensure that suitable JIRA tasks are already in place to support this scope.


4

Start Beijing Release Planning: ( 10 min)

M1 project plan for Beijing will be due before December F-F - (December 11-13, 2017, Santa Clara, CA, USA) 

Release theme seems to be carrier grade robustness

review

vnfrqts Project charter

remaining vnfrqts Epics

revise VNFRQTS/ Propose New Stories


Any other Business


meeting record


   4. Any other Business? (5 min)