Date | Project | Deliverable |
---|---|---|
July 21 | VNF Requirements | seed contributions in proper formats and repos |
July 28 | VNF Requirements | documentation tool chain generating:
|
August 1 | VNF Requirements | Sprint 1 defined |
August 3 | VNF Requirements | M2: Test Cases Defined |
August 15 | VNF Requirements | Sprint 1 complete, Sprint 2 Defined |
August 24 | VNF Requirements | M3: |
August 29 | VNF Requirements | Sprint 2 complete, Sprint 3 Defined |
September 12 | VNF Requirements | Sprint 3 complete, Sprint 4 Defined |
September 14 | VNF Requirements | M4: |
September 26 | VNF Requirements | Sprint 4 complete, Sprint 5 Defined |
September 28 | VNF Requirements | RC0 |
October 10 | VNF Requirements | Sprint 5 complete, Sprint 6 Defined |
October 12 | VNF Requirements | RC1 |
October 24 | VNF Requirements | Sprint 6 complete. |
October 26 | VNF Requirements | RC2 |
November 2 | VNF Requirements | Signoff |
...