We start our meetings by mentioning the project's Antitrust Policy, which you can find linked from the LF and project websites. The policy is important where multiple companies, including potential industry competitors, are participating in meetings. Please review and if you have any questions, please contact your company legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.

Agenda

START RECORDING

Duration

Agenda Item

Requested byNotes / Links
30 mins

Cross-project discussion


CLM Jenkins jobs are failing

Nexus-IQ was not stable, Jira was opened: IT-26799 CLM Jenkins Jobs Failing.

Progress - not all jobs are failing. Pawel's access to CLM reports was lost - Jira was opened for that: https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/IT-26825


New Delhi Release Status 

  • New Delhi RC date change (May 16 → 23) and Sign Off (June 6 → 13)
  • Project Milestone Status, New Delhi Milestone Status (work in progress)
  • New Delhi project branch ("newdelhi") creation for components with the following rules:
    • Code branch still goes with the marketing (e.g., newdelhi) 
    • If a project does not have any change (e.g., not active, no PTL), there is no branch change; if necessary, create dummy branches
    • Likewise, helm chart versioning is needed for active projects only. If there is no project change, they can stay at the old helm chart versions
      • The new OOM scripts (thanks to Andreas) support this
  • New Delhi Architecture Diagram, New Delhi-R14 Architecture Diagram
  • Oslo related Wiki under creation by Byung, Release Planning: Oslo
    • TSC voting this Thursday May 16th for Release Candidate
    • Oparent removal from Oslo?? Will discuss it with SECCOM and OOM, too
  • New releases (list of version under prep by SECCOM):
    • K8s - 1.28.6 version  → 1.29.x
    • ISTIO 1.21.x planned 

Waiting for an update from SDNC - do we have a conclusion from discussion between Sunket and Dan?

  •  Action Pawel to send an e-mail to Dan, Andreas and Byung in cc.

Policy team had to disable Drolls component in OOM. Work could be continued in the next release. 

NG Portal images are available. CR for Docs prepared. 

New Delhi Branches

Need info about branches that DOC needs to create and branches to be created by projects.
note: remove deprecated projects
New Delhi Project branch, document and release note for New Delhi requests were sent to PTLs. Any update?

LF IT Support


  •  Ticket to be opened by Thomas Kulik - those repositories have no owners which blocks Documentation projects 
  •  Archiving old projects at the TSC level - next TSC meeting Paweł Pawlak 
  •  Thomas and Andreas will have a meeting on April 9th.

Pending tikect opened by Marek:

https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/IT-25573

Testing Environment


Testing Improvement



CSIT Review



ToolChain Improvement



Documentation

Other Improvement suggestion

DMaaP MR deprecation: SDNC listener removal is done. A&AI dependency removal is done. 


Plan to migrate ONAP components to use RFC8040. Any update? No Update from Dan. We may need to move it to Oslo.

----

As backup Dan is working on Biermann but not progressed. ODL is not supporting it. Restconf stack is based on RFC draft. 

  • Preferred approach is to move to RFC8040 (Alternative 1).
    • Originally proposed back in the Kohn release 
    • Plan for the New Delhi release
    • Andreas Geißler DT has someone working on the SO piece to try and port to RFC8040
    • ONAP components will be moved to RFC8040 in New Delhi
  • Alternative 2: keep maintaining Biermann interface.
    • may support either London or Montreal as a long term release
  • Alternative 3: rollback to version before Argon.
  • Alternative 4 (the most drastic): stay where we are for now and begin to work with moving off from ODL.  

As we have no solution, we can not move to ODL Potasium.

RFC changes ongoing, master to be tested this week for SO.

Andreas to prepare environment for tests, so SDNC could be updated.

Subcommittee Updates for PTLs

  1. Recommended packages upgrades are available on the restricted Wiki. Jiras are created per project. 

    Need to check NG Portal status CLM jobs. Any update?


Ticket opened by Fiete: https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/IT-26527 (ticket is closed)

  •  ongoing; Jessica and Fiete are discussing this.

We are missing NG Portal UI CLM job.

List of the ONAP components to be disabled prepared by Andreas: 

OOM New Delhi Release

On April 18th, TSC approved the list.


Sharing Best Practices




Others



IF TIME ALLOWS ....
15 minsRelease status






5 minsUpcoming Events


    • TBD
10 minsRemaining Action Items



Zoom Recordings

GMT20240603GMT20240610-125846125859_Recording_2560x1440.mp4

GMT20240603GMT20240610-125846125859_Recording.transcript.vtt

...