  • Antitrust Policy Notice

We start our meetings by mentioning the project's Antitrust Policy, which you can find linked from the LF and project websites. The policy is important where multiple companies, including potential industry competitors, are participating in meetings. Please review and if you have any questions, please contact your company legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.

Agenda

START RECORDING

Duration

Agenda Item

Requested byNotes / Links
30 mins

Cross-project discussion


  • This meeting is reduced to 30 minutes
  • Rotating host

New Delhi Release Status 


LF IT Support


IT Jira issue review

  • Dashboard
    • Some jobs still failing when attempting to republish artifacts. Matt working on workaround
  •  discussed on Jan 15;  Matt, any update? It is resolved.


GItHub Actions Job failing on RTD verification

https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/IT-26426

Testing Environment


Testing Improvement



CSIT Review



ToolChain Improvement



Documentation

Other Improvement suggestion


Andreas Geißler 

TSC approved confirmed that according to regular ONAP policy releases prior to London will not be supported for AAF certificate issues.

Spark, Tata and Bell Canada to be informed about this issue.


SDNC cannot be updated for Biermann

  •  Dan Timoney, Andreas will send email for this issue to Dan this week. We need to resolve it for New Delhi.

Subcommittee Updates for PTLs



Sharing Best Practices



IF TIME ALLOWS ....
15 minsRelease status






5 minsUpcoming Events


10 minsRemaining Action Items



...