15 | Release Status | | Guilin - M2/ M3 Review - NO GO
- Guilin Release Requirements - Guilin M2/M3 Review
- Use Cases - 100% on track
- Functional Requirements - 71% on track; 19% mitigated; 10% no scorecard (REQ-334-info provided during TSC Call, REQ-388)
- S3P - 43% on track; 46% mitigated; 4% red (REQ-379); 7% no scorecard (REQ-369-info provided during TSC Call, REQ-350)
- Reduced Scope: REQ-385, REQ-345; REQ-340
- Candidates for '30 mins PLT practice': REQ-323, REQ-350, REQ-376, REQ-396 - #ACTION: Req Owners, please attend PTL Call on 8/10
- TSC VOTES
- REQ-379 - #AGREED the TSC agrees that only GPL v3 should be removed from the containers for the Guilin Release, distributed by the ONAP Community
- #AGREED the TSC approves any requirement marked as "Green" and "Yellow" as "GO" for M2/M3
- Milestone status - 83% Completion - Congratulations to CLAMP, CCSDK, Holmes, SDNC !
- #AGREED the TSC approves CLAMP, SDNC/CCSDK, Holmes projects as successfully passing their M2/M3 milestone.
- Architecture Subcommittee to reviews:
AAI, CLI, DCAE (8/4?), DMaaP (7/14?), Modeling, MSB, MultiCloud, Portal (8/6?), UUI, VFC, VID, VVP; VNFSDK #ACTION (David/Catherine) Recheck Architecture wiki - ONAP Architecture Component Description - Guilin (-R7) Release (New) - #ACTION (chaker): Add VID to component review list
- SO - Waiver requested to completed API by 8/17
- Remaining Tasks: Data Model/API docs, code review/merge, risk to be reviewed/updated, Bug fixing
- Guilin Risks
- Next steps
- Requirement Owners to update their M2/M3 scorecard no later than August 11th EOD (RED-350, REQ-388)
- Architecture Subcommittee to schedule a meeting with remaining projects within the next two weeks
- Projects to complete their remaining tasks by August 11th EOD? Then request a waiver on the wiki - Guilin Milestone and Requirements Exception Requests that will be reviewed with the TSC on August 13th, 2020
Maintenance Releases - Frankfurt - Release notes: https://gerrit.onap.org/r/c/doc/+/110747
- Remaining Tasks: Tagging in progress - "6.0.1-ONAP"
- Target Delivery Date: August 17th, 2020
- El Alto - NO GO
- Daily Gating chain is OK
- Working on remaining issues
|