Need to check which use cases are missing between Frankfurt Release Requirements and 2: Frankfurt Release Integration Testing Status - missing #45, 43 etc.
"Verify readiness of release artifacts" to be assigned to Morgan Richomme who will give the greenlight
Next RC2 review during PTL Call on 6/1 - bank holidays in Europe so offline status will be required
Finalize the Release Note
SECCOM will provide inputs for the Security section for each project
Document the current upgrade component strategy => provide the link under "Finalize the documentation" JIRA Management RC2 and add the link to the Readthedoc as well. For Guilin, special template in the RTD.