Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Duration

Agenda Item

Requested byNotes / Links
1 hour

Cross-project discussions

New Policy API 

LF IT Support

Jessica Gonzalez
  • roadmap for pylint implementation
    • Try to align pylint for all the projects
    • It has been prototyped by several projects
    • Not blocking the code but it provides information to the PTLs regarding the quality of submitted code
    • It will be part of the Jenkins verify jobs
    • ACTION: pylint will be implemented in all the projects as an informational tool (similar to checkstyle for JAVA) for the PTLs/Committers about the quality of submitted code.It will be part of the verify Jenkins job but it will not return verify -1 by default except if PTL will raise the request to block the code. No action for the TSC.
  • IT-18078 integration/xtesting
    • Jessica says e-mail sent to TSC mailing list. Waiting for TSC approval.
    • ACTION: Kenny to review issue and determine need for TSC vote.
  • Issue with the Frankfurt Maturity Matrix - Frankfurt Release Platform Maturity v1
  • When trying to update then getting the following message

I have tried to create v1 to fix the issue but the problem re-occurred.

ACTIONS:

#1 Seshu will create a ticket to fix v1 Platform Maturity

#2 Jess will fix the current wiki page which is a current blocker for PTLs to complete their M1

#3 Jess will send a notice to onap-release, onap-tsc mailing list to provide guidelines in order to avoid this behavior in the future (not discard update?)

  • ONAP JIRA issue - RELENG-2517 -ONAP JIRA has invalid resolution type resulting in confusing behavior

       Old issue - maybe let's remind the ONAP Community about this limitation?

Testing Environment

Testing Improvement

  • Currently few failing jobs - please direct attention to getting these tests functioning correctly.
  • Will continue to review here (ptl mtg)
  • Useless CSIT test elimination

ToolChain Improvement

  • El-Alto Retrospective - please submit your feedback by Nov 15th - these will be reviewed during the PTL Call on 11/18.
  • Release Note Template

Other Improvement suggestion

S3P Security maturity update proposal: Add at least 2 sections: vulnerabilities remediation  (OJSIs management + known vulnerabilities) and increased tests code coverage (example could be increase by 5% for each project).

Known vulnerabilities management - PLEASE complete your analysis, respond to comments for El Alto release. Table

Current OJSI performance Analysis

Still 38 OJSI tickets related to HTTP open while we expose only ~20 HTTP ports. We can close almost half as soon as we get the commit hash-id

Worst performing projects
  • CLI
    • 4 OJSI tickets open
    • 1 ticket with CVE
    • No activity at all
  • Logging
    • 9 OJSI tickets open
    • 1 ticekt with CVE
    • Very limited activity
  • MSB
    • 11 OJSI tickets open
    • 1 ticekt with CVE
    • No activity at all
Could be improved
  • APPC
  • DMAAP
  • INT
  • SDNC
  • SO
Please follow them
  • CLAMP
    • Average response time ~1 day
    • More advanced fixes provided in less than a month
  • Policy
    • Prompt response
    • Following the procedure
    • No open issues.
  • Portal
    • Recognition for the hard work
    • Not everything fixed yet but good progress made

OOM Helm charts password removal

Heads-up: Information (not the code) requested by the SECCOM must be provided as part of the Frankfurt release. Otherwise the component and its associated use cases/requirements will be descoped from the ONAP Frankfurt release. SECCOM will provide a proposal to the TSC on 10/31.

Subcommittee Updates for PTLs

cl664y@att.comTSC El-Alto Demo Contest - DEMOS - R5 El-Alto Demos
  • Submission open till Nov. 8th, 2019
  • EAUG/TSC review/vote: from Nov. 11th to Dec 4th, 2019

Sharing Best Practices



IF TIME ALLOWS ....
20 minRelease status

Incoming EventsKenny Paul
  • PTL call is now planned @3pm CET, 9am EST, 6am PST, 8am CST, 10pm China Time, 7.30pm Indian Time
  • ONAP/CNTT F2F Event in January 13-16th, 2020 - Prague - Registration https://events19.linuxfoundation.org/events/lf-networking-ddf-plugfest-2020/
  • ONAP 2 day event before or after ONES North America (April 20&21) - Los Angeles (TBC)
  • ONAP DDF planned in June - under planning
  • ONAP 2 day event before or after ONS North Europe - Antwerp (TBC)
  • Survey coming from LFN for Dec OR Jan for steady-state full DDF meetings to all LFN communities & locations
10 minsRemaining Action ItemsPTL Weekly ONAP12, Mon UTC 13:00

...