Duration

Agenda Item

Requested byNotes / Links
START RECORDING AntiTrust Message
10minCSIT review

Currently few failing jobs - please direct attention to getting these tests functioning correctly.

Useless CSIT test elimination

20 minsEl-Alto Release

Project Status in El-Alto Release

10minFrankfurt Planning - Focus on the subcommittees 
  • Frankfurt schedule review
  • Frankfurt Release Requirements
    • Requirements freeze - Sept 27
    • 41/44 requirements with corresponding JIRA issues in REQ
  • oparent/AAF/CCSDK/Portal/SDC SDK released jar artifacts - need a deliverable milestone (M3? before M4) David McBride
  • SECCOM recommendations for Frankfurt various software platforms upgrades 
    • Programming languages
    • Docker, Kubernetes
    • Alpine
    • Databases
      View file
      name19_10_14_ONAPSoftwarePlatformVersionUpgradesV2.pptx
      height150
  • Python2 to python3 upgrade is a requirement for Frankfurt - 
    Jira Legacy
    serverSystem Jira
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyREQ-174
     
10minONAP deliverables outside the releasecl664y@att.com

The following activities are implemented outside the normal cycles by the project teams:

  1.  Completion of Self-Serve releases (Jessica Wagantall )
  2.  Dockerhub migration (Cristina Pauna )
  3.  Move OOM Helm Charts ownership to project team (Mike Elliott )
  4.  Ingress Controllers (Krzysztof Opasiak)
15minDockerHub Migration updatecristinapauna

Cross project dependencies

onap-discuss message: https://lists.onap.org/g/onap-discuss/topic/dockerhub_migration_and/34447632?p=,,,20,0,0,0::recentpostdate%2Fsticky,,,20,2,0,34447632

wiki: Migration to DockerHub

From TSC Chat:

"The proposal is to generate the release tag only by the release Jenkins job (now it's also generated by the staging job). I will not be able to join the PTL meeting next week, so I will go to the OOM and CSIT meetings next Wednsday to discuss it. I will come back next week at the TSC meeting with the result."

5minLF Infrastructure/Rel process
10 minsRemaining Action ItemsPTL Weekly ONAP12, Mon UTC 13:00
15minONAP release cadence Chaker Al-HakimExplore release process cadence

...