START RECORDING AntiTrust Message
10minCSIT review

Still significant failing jobs - please direct attention to getting these tests functioning correctly.

Useless CSIT test elimination

Target completion as part of Frankfurt - keep going !

20 minsEl-Alto Release

Project Status in El-Alto Release

Action (follow with Owners): Actions

  • 2: El Alto Release Integration Testing Status - check with all owners to get their latest status ASAP
  • OOM to review OOM-2117
  • CL Loops in progress but facing some issues (Marco will follow-up)
  • Expectations to get a new SO container (Staging available but need the 'Release' version by 10/2)
  • Shankar is reporting some concerns about CADI issue related to AAF => reverting changes associated to the new CADI and will deliver a new OOF container
    • Christopher MCcray will follow up with Jonathan - new CADI to be planned as part of Frankfurt, no time to fix this as part of El-Alto
    • Christopher McCray to check if any other component is impacted
10minFrankfurt Planning - Focus on the subcommittees 

Frankfurt Release Requirements

Frankfurt Next Milestones

  • Frankfurt Requirements to be frozen by Sept 27th, 2019 so TSC can start to review/prioritize them.
  • Prioritization to be completed by Oct 3rd, 2019.
  • M1 currently planned on Oct 10th, 2019.
10 minLF Infrastructure/Rel process
10 minDocumentation HackathonSofia WallinReadout on hackathon organised at the ONAP DDF
10 minsRemaining Action ItemsPTL Weekly ONAP12, Mon UTC 13:00

...