Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

DurationAgenda ItemRequested byNotes / Links
START RECORDING
30min

Dublin end game plans


RC2 Follow-up

Sign-off - June 6th

RC2 Follow-up

  • Latest "Release" Images?
  • Dublin release branch
  • Pair-wise Testing: Integration Weather Board for Dublin Release - Integration Weather Board for Dublin Release
    • Current Completion Status: Portal (77%) and S0 (89%)
  • Test Coverage Waiver Request

      JIRA Query - Remaining 675 Items

status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "Dublin Release" ORDER BY key ASC, priority DESC, updated DESC

  • No Medium, Low, Lowest defect to be fixed at this stage on Dublin branch - only High/Highest


Please provide your Sign-Off checklist no later than June 5th 11am PST- thank you

Deliverables for Release Sign-Off Milestone Checklist Template

15 minsAlpine upstream packaging changed - breaking the ONAP build - CIA team to review and recommend long term strategyAdolfo Perez-Duran

View file
nameonap-base-images-lcm-ptl.pdf
height250

20 minNexus → Dockerhub MigrationBrian Hedstrom Paul-Ionut VaduvaJessica Gonzalez

View file
nameONAP Multi Arch Support PTL 06-03-19.pdf
height250

DEFER TO June 10

15 MinsEl Alto Release

Review/update your JIRA El Alto Content to be aligned with the scope a.k.a. “Reduce Internal Debt” (Every 4 ONAP releases)

  • Refactoring
  • JIRA Backlog Reduction (defects, etc.)
  • Vulnerability issues
  • Test Coverage including jS
  • Test Automation & CI/CD pipeline
  • Deployment procedure (including Upgrade Strategy)
  • Documentation
  • etc.

There are currently

-85 items where affectedversion is “El Alto release”

JIRA Query

status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and affectedVersion = "El Alto Release" ORDER BY key ASC, priority DESC, updated DESC

-1479 items where fixversion is “El Alto release”

JIRA Query

status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "El Alto Release" ORDER BY key ASC, priority DESC, updated DESC

DEFER TO June 10

10 minsEl Alto release

Known vulnerabilities analysis for Dublin takeaways: 

  • identification of packages for upgrade, agreement on the target release
  • identification of packages for replacement, agreement on the target release

and coordination of action items between teams

...