zoom bridge: https://zoom.us/j/283628617
...
Duration | Agenda Item | Requested by | Notes / Links |
---|
START RECORDING |
30min | Dublin end game plans
Sign-off follow-up | |
Sign off Follow-up: - Latest "Release" Images?
- Security Feedback - Vulnerability Tables, CII Bagding, Release Note, OSJI, etc. - 26 CVE issued, pushing updates of release notes - please merge ASAP
- Integration Blockers: Dublin Release Integration Test Blocking Issues
- Remaining Highest/High Defects: Defect Status for Dublin
- Integration Tests Status: Dublin Release Integration Testing Status
34 use cases/functional/non-functional requirements require E2E testing. 29 out of 34 are completed (including N/A) 2 out of 34 are at >=90% test completion - 5G - OOF/PCI - completion 6/21 too late - need to wrap-up on 6/17 EOD
- Change Management - Flexible Designer & Orchestrator - no completion date - need to wrap-up on 6/17 EOD
2 out of 34 <90% test completion => Reduced scope to be communicated to the LF Marketing Team
- CCVPN
- Consistent ID of a Cloud Region
1 out of 34 de-scoped from release (vCPE with TOSCA)
- Documentation Tickets: Documentation Status for Dublin
- Projects: Project Status in Dublin Release
- 29 projects (excluding Doc) - Sign-Off
- 23 out of 29 are completed
- 6 out of 29 are in progress - blockers and/or documentation - APPC, Policy, OOF, SDC, Logging & Integration
- Dublin release branch NOT created – Long list to the right.... except Documentation since 5/15 (so cherry-pick)
- Please update Readthedoc asap - Dublin Release Notes
- Review Marketing Messages - https://lists.onap.org/g/onap-discuss/message/17065
- Please update JIRA bugs, tasks, user stories, etc, but do not close tickets when the work is not done
JIRA Query - Remaining 508 Items (was previously 491?)
status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "Dublin Release" ORDER BY key ASC, priority DESC, updated DESC |
5min | Lab situation | | We are having severe issue with lab (can hardly deploy ONAP). Lab admin suggested to cut CPU usage by half |
15min | El Alto Release | | Review/update your JIRA El Alto Content to be aligned with the scope a.k.a. “Reduce Internal Debt” (Every 4 ONAP releases) - Refactoring
- JIRA Backlog Reduction (defects, etc.)
- Vulnerability issues
- Test Coverage including jS
- Test Automation & CI/CD pipeline
- Deployment procedure (including Upgrade Strategy)
- Documentation
- etc.
There are currently -85 items where affectedversion is “El Alto release” JIRA Query status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and affectedVersion = "El Alto Release" ORDER BY key ASC, priority DESC, updated DESC -1479 items where fixversion is “El Alto release” JIRA Query status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "El Alto Release" ORDER BY key ASC, priority DESC, updated DESC
<<El Alto Proposal Here>> |
20 min | Nexus → Dockerhub Migration | Brian Hedstrom Paul-Ionut VaduvaJessica Gonzalez | View file |
---|
name | ONAP Multi Arch Support PTL 06-03-19.pdf |
---|
height | 250 |
---|
|
|
15 min. | Client Cert Generation | |
|
5min | Security in El Alto Proposal | Paweł Pawlak |
|
...