zoom bridge: https://zoom.us/j/283628617

...

DurationAgenda ItemRequested byNotes / Links
START RECORDING
30min

Dublin end game plans


Sign-off follow-up


Sign off Follow-up:

  • Latest "Release" Images?
  • Security Feedback - Vulnerability Tables, CII Bagding, Release Note, OSJI, etc. - 26 CVE issued, pushing updates of release notes - please merge ASAP
  • Integration Blockers: Dublin Release Integration Test Blocking Issues
  • Remaining Highest/High Defects: Defect Status for Dublin
  • Integration Tests Status: Dublin Release Integration Testing Status
    • 34 use cases/functional/non-functional requirements require E2E testing.

    • 29 out of 34 are completed (including N/A)

    • 2 out of 34 are at >=90% test completion

      • 5G - OOF/PCI - completion 6/21 too late - need to wrap-up on 6/17 EOD
      • Change Management - Flexible Designer & Orchestrator - no completion date - need to wrap-up on 6/17 EOD
    • 2 out of 34 <90% test completion => Reduced scope to be communicated to the LF Marketing Team

      • CCVPN
      • Consistent ID of a Cloud Region
    • 1 out of 34 de-scoped from release (vCPE with TOSCA)

  • Documentation Tickets: Documentation Status for Dublin
  • Projects: Project Status in Dublin Release
  • 29 projects (excluding Doc) - Sign-Off
    • 23 out of 29 are completed
    • 6 out of 29 are in progress - blockers and/or documentation - APPC, Policy, OOF, SDC, Logging & Integration
  • Dublin release branch NOT created – Long list to the right.... except Documentation since 5/15 (so cherry-pick)
  • Please update Readthedoc asap - Dublin Release Notes
  • Review Marketing Messages - https://lists.onap.org/g/onap-discuss/message/17065
  • Please update JIRA bugs, tasks, user stories, etc, but do not close tickets when the work is not done

      JIRA Query - Remaining 508 Items (was previously 491?)

status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "Dublin Release" ORDER BY key ASC, priority DESC, updated DESC

5minLab situationWe are having severe issue with lab (can hardly deploy ONAP). Lab admin suggested to cut CPU usage by half
15minEl Alto Release

Review/update your JIRA El Alto Content to be aligned with the scope a.k.a. “Reduce Internal Debt” (Every 4 ONAP releases)

  • Refactoring
  • JIRA Backlog Reduction (defects, etc.)
  • Vulnerability issues
  • Test Coverage including jS
  • Test Automation & CI/CD pipeline
  • Deployment procedure (including Upgrade Strategy)
  • Documentation
  • etc.

There are currently

-85 items where affectedversion is “El Alto release”

JIRA Query

status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and affectedVersion = "El Alto Release" ORDER BY key ASC, priority DESC, updated DESC

-1479 items where fixversion is “El Alto release”

JIRA Query

status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "El Alto Release" ORDER BY key ASC, priority DESC, updated DESC


<<El Alto Proposal Here>>

20 minNexus → Dockerhub MigrationBrian Hedstrom Paul-Ionut VaduvaJessica Gonzalez

View file
nameONAP Multi Arch Support PTL 06-03-19.pdf
height250

15 min.Client Cert Generation
5minSecurity in El Alto ProposalPaweł Pawlak

...