DurationAgenda ItemRequested byNotes / Links
START RECORDING
30min

Dublin end game plans

RC1 - May 16th

RC2 - May 30th (Euro holiday)

Sign-off - June 6th

RC1 Follow-up: Deliverables for RCx Milestone Checklist Template


5 minImage release plan before 6/6

Unreleased images used in OOM: http://onapci.org/

RC1 image release by this Thursday 5/23

RC2 image release by next Thursday 5/30

No more image release accepted by Integration after 5/30, unless explicitly asked by Integration and those images can ONLY contain bug fixes required by Integration

20 minNexus → Dockerhub MigrationBrian Hedstrom Paul-Ionut Vaduva Jessica Gonzalez
10 minAlternatives Vulnerability fixes delivery vehicle - El Alto early drop vs. Dublin Maint Release

We need to repair the vulnerabilities w/in 60 days of disclosure for CII Badging. 

Problem statement: What is the preferred method of delivering critical fixes atop Dublin within 60 days?

Some alternatives:

  1. Mid-El-Alto release candidate test cycle to validate component releases?
  2. Dublin maintenance release?
10minSECCOM update - unresolved CVE review & other security followups

Events reminderFormer user (Deleted)

https://lists.onap.org/g/onap-tsc/topic/june_ddf_registration_is_now/31435252?p=,,,20,0,0,0::recentpostdate%2Fsticky,,,20,2,0,31435252

...