...
Duration | Agenda Item | Requested by | Notes / Links |
---|---|---|---|
START RECORDING | |||
30min | Dublin end game plans RC1 - May 16th RC2 - May 30th (Euro holiday) Sign-off - June 6th | RC1 Follow-up: Deliverables for RCx Milestone Checklist Template
| |
5 min | Image release plan before 6/6 | Unreleased images used in OOM: http://onapci.org/ RC1 image release by this Thursday 5/23 RC2 image release by next Thursday 5/30 No more image release accepted by Integration after 5/30, unless explicitly asked by Integration and those images can ONLY contain bug fixes required by Integration | |
20 min | Nexus → Dockerhub Migration | Brian Hedstrom Paul-Ionut Vaduva Jessica Gonzalez | |
10 min | Alternatives Vulnerability fixes delivery vehicle - El Alto early drop vs. Dublin Maint Release | We need to repair the vulnerabilities w/in 60 days of disclosure for CII Badging. Problem statement: What is the preferred method of delivering critical fixes atop Dublin within 60 days? Some alternatives:
| |
10min | SECCOM update - unresolved CVE review & other security followups | ||
Events reminder | Former user (Deleted) |
|
...