Duration 60 minutes

DurationAgenda ItemRequested byNotes / Links
START RECORDING
30min

Dublin end game plans

RC1 - May 16th

RC2 - May 30th (Euro holiday)

Sign-off - June 6th

RC1 PreparationFollow-up: Deliverables for RCx Milestone Checklist Template

20 minNexux → Nexus → Dockerhub MigrationBrian Hedstrom Paul-Ionut Vaduva Jessica Gonzalez
10 minAlternatives Vulnerability fixes delivery vehicle - El Alto early drop vs. Dublin Maint ReleaseWe need to repair the vulnerabilities w/in 60 days of disclosure for CII Badging. 
15 minsAlpine upstream packaging changed - breaking the ONAP build - CIA team to review and recommend long term strategyAdolfo Perez-Duran