Duration | Agenda Item | Requested by | Notes / Links | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
START RECORDING | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5min | Casablanca Maintenance Release
| Missing Information in the Casablanca Maintenance Release Note:
Document theses known issues:
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5min | M1 Milestone Approved by TSC - 28 out 30 projects Integration/Documentation projects conditionally passed Functional/Non-Functional/Use case scope:
Dublin M1 Follow-Up Next Milestone: Functional Freeze in 2 weeks (2/14) |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10min | S3P Review | M1 SP3 Checkpoint: https://lists.onap.org/g/onap-tsc/message/4540
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15min (10 min preso 5min Q&A) | Multi-architecture support Overview of ARM testing/support impacts investigation
|
Costs/Resource impacts to be provided
70+ jenkins jobs already running: https://jenkins.onap.org/view/arm64/ #Info-confirmation provided by Adolfo that there is no impact on LF infrastructure (no additional cost- extra infrastructure provided by ARM; no additional IT support-completely handled by ARM team). #Action (LF/Adolfo): Need to confirm that there is no extra cost to host the containers. #Action (Paul-Ionut Vaduva /Adolfo/Yang): Provide additional clarifications about the Test Strategy including the resources plan on the next PTL Call (2/11) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5min | 5G Use Case | Benjamin Cheung |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5min | Distributed Analytics | Srinivas Tadepalli | Distributed Analytics - need to move from func requirements to use case (deliver as POC) srinivas tadepalli Marco Platania Yang Xu work together to identify another repositiory than demo - to be followed on 2/4 on PTL call | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5min | Security | Are sufficient tasks defined for all project | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5min | ONAP CLI | AAI, SDC, SO, Policy, APPC, SDNC and MSB CLI commands in Dublin release? | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10min | Datalake approved as a POC Start to discuss project impact either as producers of for example Elasticsearch as a Service or as consumers of for example multitenant MySQL/MariaDB/PostregSQL aaS and for new services like Containerized Hadoop as a Service | From TSC meet | Jiras so far
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale/Internationalization language support | Need to confirm testing resource to Yang Xu and what they will be able to test - to be concluded on 2/4 |
...
- Casablanca Release Maintenance
- (Catherine/Team): Finalize the ONAP Casablanca Maintenance Release Note.
- (Catherine/Team): Finalize the ONAP Casablanca Maintenance Release Note.
- Dublin Release:
- 2/11: Owners/PTLs to work together on Conditional scope (Yellow items): https://wiki.onap.org/display/DW/Dublin+Release+Requirements
- 2/11: Procedure to be provided concerning CSIT moving to OOM
- 2/11: Migrate Docker image releases from Nexus3 into Docker Hub (Architecture Independence) by Dublin M4. See more information: Future of Releases in LF Releng
- 2/13 (or earlier): M2 Checklist completed
- 2/11 (Amy/Yang): to work on oParent scope and timeline
- Others:
- (PTLs) will take over the ownership of the INFO.yaml file for addition/deletion of committers for the repo
- (PTLs): Review ONAP codebase license scan, Jan. 2019 sent by Steve Winslow on 1/18
- (Mike Elliott) will work with PTL to gather/transfer knowledge and create training materials. Targeted projects: A&AI, Log, Policy, APPC, CLAMP and ONAP CLI.
- (Integration): Provide a procedure about the Manifest including dependencies, timers, etc.
- (Jimmy Forsyth): Identify projects impacted by AAI-1989
...