- Dublin Release:
- 1/17: M1 review for all the projects except Integration. Final checklist submitted no later than Thursday Jan. 17th, 9am CET/10am Israel Time/4pm China Time/3am EST
- 1/24: M1 review for Integration.Final checklist submitted no later than Thursday Jan. 24th, 9am CET/10am Israel Time/4pm China Time/3am EST
As part of your M1 activities, - Please review your M1 S3P Actual and provide your S3P M1 target: https://wiki.onap.org/display/DW/Dublin+Release+Platform+Maturity
- Please update any risk/issue (if any): https://wiki.onap.org/display/DW/Dublin+Risks
- Please provide your commitments on the centralized wiki: https://wiki.onap.org/display/DW/Dublin+Release+Requirements
-
WindRiver Lab Management
Action to be completed no later than January 31st, End of your DayReply to Stephen Gooch concerning current usage.
If no response then
- any tenant space, VM not used over the last 3 months will be deleted.
- Any person not log to Windriver over the last 6 months then account will be delateddeleted
- Committer(s)/Calendar Requests
Kenny & Jim will review the following items and will provide feedback no later than our next TSC Call (1/17):
#1 DmaaP zoom bridge issue => Need to identify 1 slot from DMaaP Team
#2 AAF - Add Sai committer's rights
#3 Remove inactive Modeling committers - https://lists.onap.org/g/onap-tsc/message/4450
#4 CCSDK zoom bridge
#5 VNFREQ - Helpdesk #'s #66481, #65633 and #64787
...