Agenda Items | Presented by | Time | Notes / Links | JIRA Tasks |
---|
Casablanca Release Status | | 30 mins | New reporting proposal & Latest status Integration Status View file |
---|
name | ONAP Casablanca TSC Oct4.pdf |
---|
height | 250 |
---|
|
Notes: Legend for Releae status review: RED- require TSC support/attention; Yellow - not perfect but team is working on it ; Green - on track - For platform maturity, T is the target level and A is the achieved level
- Action Items:
- Review Casablanca Platform Maturity scorecard with PTLs
- Jason & Securtiy Subcommittee to work with PTLs and assess if current S3P status acceptable or not - feedback expected for RC0
- Legend to be added to Casabkanca Platform Maturity
- PTL Prioritization:
- RC0: Healthcheck, pair-wise, AAF integration, vFW, vDNS
- RC1: Stability, Resiliency
Overall Status: Expected next week "green status" for all healthchecks
|
|
Any Infrastructure Improvement/Plan | | 10 mins | Lesson Learned - Nexus? Notes: - Action Item for LF (Jess): provide ETA concerning Nexus issue by Oct 5th - short term solution to unlock PTLs and long term (extension of capacity)
|
|
Incoming ONAP Events | | 10 mins | - F2F Architecture/(Modeling) Meeting in Montreal
Oct 29nd-31st - V2F Dublin Release Meeting
Week of Nov 19th?- Notes:
- F2F Event Week of Jan 7th, hosted by Nokia?
- Action Item (Catherine): Create Doodle to decide about the V2F Dublin Release Meeting date
| Jira Legacy |
---|
server | System Jira |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-10 |
---|
|
Jira Legacy |
---|
server | System Jira |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-7 |
---|
|
|
TSC Activities and Deadlines | | 15 mins | TSC Transformation? TSC Dashboard Presentation (https://jira.onap.org/projects/TSC/summary) Urgent activities: - 2019 Budget Plan by Oct. 17th Board Meeting
- EUAG Survey by Oct 25
- Identify a TAC representative
| Jira Legacy |
---|
server | System Jira |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-8 |
---|
|
Jira Legacy |
---|
server | System Jira |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-1 |
---|
|
Jira Legacy |
---|
server | System Jira |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-11 |
---|
|
Jira Legacy |
---|
server | System Jira |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-14 |
---|
|
|
New Task Force Request (s) | | 15 mins | What do we want to accomplish with Dublin to support our primary goal: Accelerate adoption of ONAP in production. - Notes:
- (Michael): acumos consumes artifacts and architecture from ONAP - raised JIRA to formalize the sync (TSC-15)
Dublin Areas - Target: Oct 25th. - Project enhancements (PTLs)
- Non Functional requirements including Operational Readiness
Definition of ONAP Orchestrator Functionalities - Project & Subcommittee Best Practices (i.e. CI/CD, E2E etc)
- Use Cases
- Deployment Capabilities - ONAP Self-Serve
- Release Packaging
| In progress Jira Legacy |
---|
server | System Jira |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-13 |
---|
|
|
Additional housekeeping | Linux Foundation | 10 mins | No update this week |
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
...
...
...
Goal is to identify the main functionalities required for orchestration, and have community focus on them.
Goal is not to park other functionalities, but to have good awarness and focus on the critical gaps being currently there.
...
...
...
Looking to have this for the Oct. 17th Board Meeting
Jira Legacy |
---|
server | System Jira |
---|
serverId | 4733707d-2057-3a0f-ae5e-4fd8aff50176 |
---|
key | TSC-8 |
---|
|
...
...
Zoom Chat Log
...
- Casablanca Status: Review Casablanca Platform Maturity scorecard with PTLs
- Casablanca Status: Jason & Securtiy Security Subcommittee to work with PTLs and assess if current S3P status acceptable or not - feedback expected for RC0
- Casablanca Status: Legend to be added to Casabkanca Casablanca Platform Maturity
- LF (Jess): provide ETA concerning Nexus issue by Oct 5th - short term solution to unlock PTLs and long term (extension of capacity)
- (Catherine): Create Doodle to decide about the V2F Dublin Release Meeting date