DurationAgenda ItemRequested byNotes / Links
START RECORDING
5 mHousekeeping


10 mRelease Status
10 mIntegration Status
15 mBeijing ArchitectureChris Donley
10 mStatus of Static Code Scanning (Coverity) integration into Gerrit
Status of asd
Stephen TerrillWanting to follow-up on the status of  a status from LF perspective
10 mStatus of Beijing ArchitectureChris Donley
10 mLFN compliance/verificationChris DonleyFor discussion. Heads-up on work in progress.
10 m2018 Plans - Discuss and assemble key budget items for ONAP technical communityFrank BrocknersWe'll need to assemble the needs of the ONAP technical community and articulate those to LFN TAC.




...