Release Planning: Honolulu
Release Schedule r5 (approved Apr 15, 2021 )
Activity Log
Date | Event or Update | Milestones Affected |
---|---|---|
Apr 29 | TSC approved Honolulu sign-off | Sign-Off |
Apr 15 | TSC approved schedule (r5) | RC1, RC2, Sign Off |
Apr 8 | Proposal for RC1, RC2, Sign Off (r5) (Note: r4 proposed but not approved) | RC1, RC2, Sign Off |
Apr 2 | Proposal for RC1, RC2, Sign Off (r4) | RC1, RC2, Sign Off |
Apr 1 | Consensus with OOM and INT that RC0 requirements met (TSC e-mail vote in progress). Action to propose schedule for RC1, RC2, Sign Off | RC0 |
Mar 29 | RC0/RC1 requirements not met. Re-evaluate on April 1. | RC0, RC1 |
Mar 25 | RC0/RC1 requirements not met. Re-evaluate on Mar 29. | RC0, RC1 |
Mar 18 | TSC approved plan to merge RC0 with RC1 on March 25 | RC0 |
Mar 11 | TSC approved schedule proposal (see Mar 10 below) | RC0, RC1, RC2, Sign Off |
Mar 10 | Blocking issue reported for RC0. Propose 1 w slip to RC0 → Sign Off (r2). Sign off moves to April 8. | RC0, RC1, RC2, Sign Off |
Mar 1 | TSC approves M3 with exceptions. Exceptions to be closed by RC0. | M3 |
Feb 25 | TSC determined that there is insufficient information to make decision, so M3 pushed out 4 days to March 1 | M3 |
Feb 1 | Uploaded ONAP Honolulu r1 to show changes to M1 and M2 dates | M1, M2 |
Jan 25 | M2 approved with exceptions | M2 |
Jan 21 | Requirements not met. M2 slipped to Jan 25 | M2 |
Jan 14 | M1 approved with exceptions | M1 |
Jan 11 | Requirements not met. M1 slipped to Jan 14 | M1 |
Dec 10 | TSC approved schedule | ALL |
Dec 10 | M1 moved out 4 days to Jan 11 | M1 |
Nov 20 | Second draft posted |
|
Nov 11 | First draft posted |
|