BBS Planning



Task

Start

End

Status



Task

Start

End

Status

1

Requirement Analysis







1.1

Finalize BBS architecture

Mon 11.26.18

Tue 12.11.18

Completed

1.2

Building Team

Mon 11.26.18

Wed 12.05.18

Completed

1.3

Create Epics In Community JIRA

Tue 12.11.18

Fri 12.21.18

COMPLETED

1.4

Create user stories In Community JIRA

Fri 12.21.18

Tue 12.25.18

completed

1.5

Make Workloads, Acceptance criteria, Plan, Dependencies

Tue 12.25.18

Mon 1.07.19

completed

1.6

Low Level Design (Output specification for project design to review)

1. LLD for SDN-C & Access SDN M&C
2. LLD for SDN-C & Edge SDN M&C
3. LLD for VES Event definition
4. LLD for topology discovery from SDN M&C
5. LLD for External API
6. LLD for PRH enhancement

Mon 1.07.19

Mon 1.14.19

COMPLETED

1.7

Low Level Design review

Mon 1.14.19

Thu 1.17.19



1.8

Model freeze

Mon 11.26.18

Tue 12.11.18

Completed

1.9

Model review

Tue 12.11.18

Tue 12.18.18

completed

1.10

Model pushed to the community

Thu 1.24.19

Tue 2.05.19



1.11

API freeze

Tue 12.18.18

Tue 12.25.18

COMPLETED

1.12

API review

Tue 12.18.18

Tue 12.25.18



1.13

API pushed to he community

Thu 1.24.19

Mon 3.04.19



2

Coding







2.1

Code Checkpoint 1



Thu 3.07.19



2.2

Code Checkpoint 2



Thu 3.14.19



2.3

Code freeze

Tue 12.25.18

Mon 3.18.19



2.4

Weekly Code review

Tue 12.25.18

Fri 2.08.19



2.5

Unit test

Tue 12.25.18

Fri 2.08.19



2.6

Code pushed to the community

Tue 12.25.18

Thu 3.28.19



3

Testing







3.1

E2E Test design and demo strategy

Mon 1.07.19

Wed 1.16.19

COMPLETED

3.2

E2E Test design and demo strategy review

Wed 1.16.19

Fri 1.18.19

COMPLETED

3.3

Internal Demo review

Mon 1.07.19

Tue 3.12.19



3.4

Develop test plan

Fri 2.08.19

Tue 2.12.19

COMPLETED

3.5

Project Test case output

Fri 2.08.19

Tue 2.12.19



3.6

Project Interface self test

Fri 2.08.19

Wed 2.27.19



3.7

Integration test plan

Fri 1.18.19

Fri 1.25.19

COMPLETED

3.8

Integration Test case output

Fri 1.25.19

Sat 1.26.19



3.9

Integration test

Fri 2.08.19

Sat 3.09.19

IN PROGRESS

3.10

Internal Demo Show Round1

Mon 3.11.19

Thu 3.14.19



3.11

Internal Demo Show Round2

Mon 3.18.19

Thu 3.21.19



4

Lab Setup





completed

4.1

Development Environment (CI/CD, Code repo)

Mon 11.26.18

Fri 12.07.18

completed

4.2

Development Environment (local env, local test env)

Mon 11.26.18

Fri 12.07.18

completed

4.3

Detailed lab topology (wiring diagram)

Wed 12.26.18

Wed 1.09.19

Completed

4.4

Detailed lab topology (wiring diagram) review

Wed 1.09.19

Wed 1.09.19

completed

4.5

Material ready

Wed 12.26.18

Wed 1.09.19

completed

4.6

Demo Lab setup

Fri 2.01.19

Mon 2.25.19

completed