[ExtAPI] Beijing M1 Planning Milestone Checklist Template
DRAFT PROPOSAL FOR COMMENTS
This checklist is expected to be completed for the project to pass the M1 Release Planning Milestone.
M1 Release Planning Milestone definition
Practice Area | Checkpoint | Yes/No | Evidence - Comment | How to? |
---|---|---|---|---|
Product Management | Are Product Backlog Epics entered in Jira? | Yes | Getting issues... | |
Are Product Backlog Stories entered in Jira? | Yes | Getting issues... | ||
Are Product Backlog Stories linked to Product Backlog Epics? | Yes | |||
Are Product Backlog Stories prioritized? | Yes | |||
Is the project team ready to estimate the top Stories (for coming Sprint) in Product backlog? | Yes | |||
Is the project team ready to create a 2 weeks Sprint in Jira? | Yes | |||
Are Team Members willing to create Tasks and associate them with Stories in Jira? | Yes | |||
Has the project team plan to contribute to Platform Maturity Improvement? | Yes | ExtAPI is not included on the MVP list for the release will not be subject to the minimum recommendation for each maturity category. | ||
Release Management | Is there a Release Planning Template available and completed in wiki? | Yes | ||
Have all the "Release Components Name" been defined in Resources and Repositories (Deprecated) for your project? (this includes all Sub-Components Names, Sub-Components Repositories Names, Maven Group ID, Sub-Components Description) | Yes | |||
Have all the "Resources committed to the Release" been defined in Resources and Repositories for your project? This includes First and Last names, LFID, Email Address and Location for PTL, Project Manager, Committers and Contributors. | Yes | |||
Have new developers made themself familiar on the Onboarding Process? | Yes | |||
Is the project team aware of the Release milestone? Any misses will required TSC exception. | Yes | |||
Integration and Testing | Has the Integration Team defined the vendor equipment list? | N/A | ExtAPI has not identified any vendor equipement | |
Has the Integration Team defined the End 2 End Release Test Case? | N/A | ExtAPI is not on MVP, so E2E Test Case is not required | ||
Development | Is the Project Team committed to develop Unit Test? | Yes | ||
Has the Project Team put in place an Automated Unit Test infrastructure? | N/A | ExtAPI is not on MVP, so Automated Unit Test is not required | ||
Is the Project Team committed to create Continuous System Integration Testing (CSIT) test case? | Yes | |||
Is the Project Team committed to perform Scrum ceremonies? | Yes | |||
Are the Project Team members aware of Continuous Integration Principles (don't break the build, Fix the build,...)? | Yes | |||
Has the Project Team a clear understanding on the Code Coverage expectations? | Yes | |||
Does the Project Team understand the Free and Open Source Software (FOSS) process? | Yes | |||
Is the Project Team willing to fill out accordingly the FOSS table? | Yes | Fill out sub-pages for each project under Free and Open Source Software | ||
Is the Project Team willing to comply to the Commit Process? | Yes | |||
Does the Project Team understand the purpose of Code Review? | Yes | |||
Is the Project Team aware of the Coding Guidelines? | Yes | Development Practices (Jave Coding Style) |